Bratislava – Trnavské Mýto
Client: Slovak Republic – Bratislava
Construction time: 3 months
Construction specification:
Area of approx. 430 m²
Construction:
– Demolition of concrete / asphalt layers 50 cm thick
– Excavation H = 1.50 m and backfilling approx. 645 m³
– Paved area – drain concrete 320 m²
– Paved area made of granite cubes 320 m²